Telangana Electricity Regulatory commission guidelines for net-metering projects

  • Net-metering is now allowed upto 1 MW from earlier limit of 500 KW per project
  • The capacity allowed under net-metering is limited to 80% of the contracted demand of the client
  • For projects upto 75 KW, there is no need of electrical inspector clearance.